TCN Commissions New Bauchi 330/132kv Transmission Substation; Adds 250MW To National Grid
TCN Commissions New Bauchi 330/132kV Transmission Substation; Adds 250MW To National Grid The Transmission Company of Nigeria (TCN) has announced the successful commissioning of a new 330/132/33kV Bauchi Transmission Substation in Bauchi town. The substation, commissioned on July 3, 2025, according to a statement by TCN’s General Manager, Public Affairs, Ndidi Mbah, has added 250MW to the national grid. The project, a TCN/World Bank initiative which commenced in February 2022, comprises 2x150MVA power transformers, a 1x75MVA reactor, and other components. It is aimed at boosting power supply in Bauchi and the Northeast region. “The new Bauchi substation project commenced in…